Abandon expensive plan to relocate AMERI Plant to Kumasi - CSOs to Energy Ministry

 


The Alliance of Civil Society Organisations (CSOs) working on Extractives, Anti-Corruption, and Good Governance have urged the Ministry of Energy to abandon plans to relocate the AMERI Plant from Aboadze in the Western Region to Kumasi in the Ashanti Region.

According to the group which is comprised of 14 CSOs, the proposed relocation and its "attendant unnecessary cost additions" must be shelved and replaced with other cost-efficient measures such as retooling National Interconnected Transmission Systems (NITS) and a competitive bidding process.

We maintain that the Minister should consider other options which we believe are far optimal option than the attempts to relocate plants and its attendant unnecessary cost additions. For instance, retooling National Interconnected Transmission Systems (NITS)," the Acting Executive Director of the Centre for Extractives and Development Africa, Samuel Bekoe said in a joint statement read on behalf of the Alliance.

"Cabinet and Parliament should assume critical responsibility for the efficient planning of the sector as these decisions among others have contributed to the current economic difficulties being faced today".

The Alliance includes ACT Africa, CEDA, ACEP, Oil Watch Ghana, TAMA Foundation, Ghana Anti Corruption Coalition and TWN Africa. The rest are NRGI, IMANI Ghana, ISODEC, Tax Justice Coalition, Revenue Mobilization Africa, OXFAM and Civil Society Platform on Oil and Gas.

Decision to sole source contract

On the Energy Ministry's decision to sole source the contract on the relocation of the AMERI plant, the Alliance alleged that the move was not based on any of the exceptional justifications provided by the Public Procurement Authority Act. It further argued for a competitive tendering approach which it said would yield optimum results and cost.

The communications from the Ministry of Energy to parliament on two occasions (15th June 2022 and 1st July 2022) indicate that the justification for sole sourcing the EPC contract to Mytilineos SA was that the company had managed the plant on behalf of Ameri for six years and were the right people to be engaged," Bekoe said.

"However, this does not necessarily mean that Ghana has to contract Mytilineos or that they are the only company that is able to do the relocation of the plant."

Cost of relocation

Bekoe also stated that the cost quoted for the scope of work involved in the relocation was $25.48 million. However, the Alliance claims that the Ministry's communications to both Parliament and the Volta River Authority indicated a contract cost of $35.6 million.

The proposal from Mytilineos indicated that the contractor would be responsible for the Engineering, Procurement, and Construction works, including the balance of plant associated with the relocation, installation, and commissioning of the Ameri plant. The cost quoted for this scope of work was $25.48 million. However, the Ministry's communications to both Parliament and VRA indicate a contract cost of $35.6 million, raising questions about what accounts for the increase in the proposed amount by 40 percent," Bekoe said.

"The Ministry responds that VRA's employer's requirement occasioned the additional cost of $10.12 million for a Water Supply and Continuous Emissions Monitoring System, which expands the scope of the EPC contract. This response assumes that these additional requirements are not part of the balance of plant indicated by Mytilineos, which we find quite confusing. More importantly, water supply components and the Continuous Emissions Monitoring System are not expensive components (would not exceed $1million) of the balance of plant, which requires clarity from the Ministry on the total cost breakdown of the EPC contract for relocating the plant".

Comments

Popular posts from this blog

MTN Ghana & MTN MoMo CEOs win laurels at Ghana CEO Awards

  The Chief Executive Officer of MTN Ghana, Selorm Adadevoh ,   has been adjudged  CEO of the Year  –  Telecom  at the  2 nd  edition of the  Ghana CEO  Vision  and  Awards   held  in Accra. At the same event, the CEO of Mobile Money Limited (MTN MoMo), Shaibu Haruna was also adjudged CEO of the Year – FinTech Service Provider. Selorm  Adadevoh’s award  is in recognition  of  his   achievements   in the areas of   sustainability, leadership excellence, innovation and others  in the telecoms space  which  has contributed to  job creation to support the  growth of Ghana’s economy. Patrick Afari (r), General Manager, Supply Chain Management and General Services receiving CEO of the Year – Telecom Award on behalf of Selorm Adadevoh Receiving the award on behalf of Selorm, Patrick Afari, General Manager, Supply Chain Management and General Services ,  expressed appreciation to the organizers for the award. He  noted that  th e  award will go a long way to inspire MTN to do more for Ghanaian

EB-ACCION DISBURSES US$15 MILLION

By Fred SARPONG Ecobank-Accion (EB-Accion), a partnership between Ecobank Ghana Limited and Accion International has disbursed amount to the tune of $15 million to over 36,000 borrowers in Micro, Small and Medium Enterprises (MSMEs) sector in the country, since the institution was set up barely six months ago. Frances Adu-Mantey, the Managing Director of EB-Accion disclosed this to Business Week in Accra last week during the official opening of Accion Hub headquarters in Africa. The institution’s current portfolio stands at GH¢4 million. She stated that currently, EB-Accion have over 6100 customers who save with them throughout the four branches of the institution. According to her, in order to improve the services of the institution, Ecobank Share Services center will facilitate the technology aspect of the bank by networking all the branches of EB-Accion. Maria Otero, President and Chief Executive Officer of Accion International said that the center’s staff in Accra will provide supp

Amantin & Kasei Community Bank posts impressive growth, with over GH¢1m profit

 Amantin and Kasei Community Bank, at Amantin in the Bono East Region has posted impressive growth in all the performance indicators during 2022 financial year under review. The bank recorded profit after tax of GH¢1,055,662, representing 35.66% more over the 2021 figure of GH¢778.151. This achievement stemmed out of 49.24% gross income growth from GH¢8,143,526 to GH¢12,153,537. Total deposits of the bank went up by 36.20%, changing from GH¢50,959,848 in 2021 to GH¢69,405,591 in 2022. The bank increased loans and advances by 22.15% from GH¢14,128,017 to GH¢17,257,614. Total assets showed an appreciation of 29.32%, amounting to GH¢77,918,288 as against GH¢60,250,693 in the previous year. On the other hand, the bank posted a marginal increase in short term investments portfolio from GH¢24,439,761 to GH¢26,585,698, indicating 8.78% change. The Chairman of Board of Directors, Amantin and Kasei Community Bank, Dr. John Oduro-Boateng, disclosed this during the 18th annual general meeting of