Speculative structures disrupt Newmont’s tailings dam expansion works

 The erection of unauthorized structures on Newmont Gold Ghana Limited’s mining area is stalling expansion works of its Tailings Storage Facility (TSF) Project.

Engulfed by the hushed and greenery scenery at Dokyikrom, in the Asutifi North in the Ahafo region, sits hundreds of the speculative structures made from metallic roofing sheets.

Speculative structures, Newmont, Dokikrom, tailings dam, JBA

The illegal structures numbering over 300 however do not serve as a home or sleeping place for their owners but an abode for weeds sprouting from the ground.

As these speculative structures continue to spring up, their owners anticipate huge compensations, a practice that actors in the mining industry are displeased with.

Speculative structures, Newmont, Dokikrom, tailings dam, JBA

Speaking with Journalists for Business Advocacy (JBA) who visited the community to witness first-hand the level of speculative structures being erected, the Director of External Relations and Communication of the Ghana Chamber of Mines, Ahmed Nantogmah, bemoaned that speculative activities are bad for the mining industry, adding that the behaviour of these individuals is delaying the compensation process and holding everyone to ransom.  

This is not good for investment; the more mining projects delay due to speculative structures, the more it affects Ghana’s mining income. I think we need to work together as stakeholders to try and resolve this for peace sake,” he lamented.

Without the tailings facility expansion, where water and waste that come as by products from the mining process are stored, the mining company cannot tail anymore which may likely affect productivity.

Newmont, however, says it is working around the clock to address the delays to ensure that work progresses. The company has begun compensation and resettlement process to resettle those directly impacted by the project.

Speculative structures, Newmont, Dokikrom, tailings dam

The Manager of Communications and External Relations of Newmont Africa’s Ahafo South and North Mines, Samuel Osei assured that “For us at Newmont, we are committed to working within the regulatory framework to ensure that those impacted by our projects are adequately resettled”.

Osei explained that the resettlement is to ensure that if ever there is any impact from the tailings dam, the people do not suffer.

And per the Minerals and Mining Act, the communities that are closed to the TSF must be resettled and compensated. However, the mining company must resettle the people who have structures and are living in them. For instance, if someone has a house, and that person is living in that house, the company will rebuild a house for that person somewhere else and move him or her.

Cut-off date

Speculative structures, Newmont, Dokikrom, tailings dam
Members of JBA inspecting one of the speculative structures at Dokyikrom

Prior to the construction of the tailings dam expansion, the Environmental Protection Agency (EPA) directed the company to declare a cut-off date of 5th of July 2019 but this was moved to the 9th of July 2019 since the communication did not reach the community on earlier date.

Cut-off date means that from that day all the properties in the project area, whether they are houses, farms and all that will not be increased. Nobody can build any more houses, and farms among others. They cannot even extend their facilities.

So, what the company did was that it captured everything that was there with drone shots to cover all the properties that were there.

However, immediately after the cut-off date was announced and the people got to know that they will be resettled, others started building what mining industry watchers call speculative structures. Meanwhile, per the Minerals and Mining Act, mining operator(s) cannot pay for buildings structures or properties that were established, erected, or built after the cut-off date.

Speculative structures, Newmont, Dokikrom, tailings dam

The EPA assessed the issues and said the owners of the speculative structures do not deserve any compensation. Because there is enough evidence to prove that all the rest structures were not there before the cut-off date.

Accra meeting to address the issues

At the meeting, the EPA said in the interest of peace (similar to the Ahafo North issue) Newmont Africa should try and give them a token.

At that meeting, it was even agreed that the token should be something that would discourage people from engaging in speculative activities in the future.

The community members who engaged in the speculative activities agreed that they would take the token offered by Newmont. However, as soon as they returned to their communities, they changed their position and demanded for full compensation.

Speculative structures, Newmont, Dokikrom, tailings dam

The meeting at the Alisa was attended by the EPA, Newmont, the affected mining community members, chiefs, the DCE, the district police commander and leaders of the communities.

When the cut-off date of 5th July 2019 was declared the buildings and structures on the expansion area were few at that time, officials of Newmont Africa told a team of JBA members who visited the Dokyikrom-Tutuka community.

The structures both habitable and non-habitable Newmont recorded were over 800. The bone of contention now is some of the over 800 structures have been extended. “Just using the drone footage, we estimated that about 300 structures have been added that we haven’t even touched.

 So, it is not just the addition, but those that existed once they were inventories, and we had the codes. They added those structures more to attract more money”.

Like you have a two-bedroom house and extend it to a four-bedroom house. The communities are also asking Newmont to extend the cut-off point limit to areas that the project doesn’t reach.

Comments

Popular posts from this blog

MTN Ghana & MTN MoMo CEOs win laurels at Ghana CEO Awards

  The Chief Executive Officer of MTN Ghana, Selorm Adadevoh ,   has been adjudged  CEO of the Year  –  Telecom  at the  2 nd  edition of the  Ghana CEO  Vision  and  Awards   held  in Accra. At the same event, the CEO of Mobile Money Limited (MTN MoMo), Shaibu Haruna was also adjudged CEO of the Year – FinTech Service Provider. Selorm  Adadevoh’s award  is in recognition  of  his   achievements   in the areas of   sustainability, leadership excellence, innovation and others  in the telecoms space  which  has contributed to  job creation to support the  growth of Ghana’s economy. Patrick Afari (r), General Manager, Supply Chain Management and General Services receiving CEO of the Year – Telecom Award on behalf of Selorm Adadevoh Receiving the award on behalf of Selorm, Patrick Afari, General Manager, Supply Chain Management and General Services ,  expressed appreciation to the organizers for the award. He  noted that  th e  award will go a long way to inspire MTN to do more for Ghanaian

EB-ACCION DISBURSES US$15 MILLION

By Fred SARPONG Ecobank-Accion (EB-Accion), a partnership between Ecobank Ghana Limited and Accion International has disbursed amount to the tune of $15 million to over 36,000 borrowers in Micro, Small and Medium Enterprises (MSMEs) sector in the country, since the institution was set up barely six months ago. Frances Adu-Mantey, the Managing Director of EB-Accion disclosed this to Business Week in Accra last week during the official opening of Accion Hub headquarters in Africa. The institution’s current portfolio stands at GH¢4 million. She stated that currently, EB-Accion have over 6100 customers who save with them throughout the four branches of the institution. According to her, in order to improve the services of the institution, Ecobank Share Services center will facilitate the technology aspect of the bank by networking all the branches of EB-Accion. Maria Otero, President and Chief Executive Officer of Accion International said that the center’s staff in Accra will provide supp

Amantin & Kasei Community Bank posts impressive growth, with over GH¢1m profit

 Amantin and Kasei Community Bank, at Amantin in the Bono East Region has posted impressive growth in all the performance indicators during 2022 financial year under review. The bank recorded profit after tax of GH¢1,055,662, representing 35.66% more over the 2021 figure of GH¢778.151. This achievement stemmed out of 49.24% gross income growth from GH¢8,143,526 to GH¢12,153,537. Total deposits of the bank went up by 36.20%, changing from GH¢50,959,848 in 2021 to GH¢69,405,591 in 2022. The bank increased loans and advances by 22.15% from GH¢14,128,017 to GH¢17,257,614. Total assets showed an appreciation of 29.32%, amounting to GH¢77,918,288 as against GH¢60,250,693 in the previous year. On the other hand, the bank posted a marginal increase in short term investments portfolio from GH¢24,439,761 to GH¢26,585,698, indicating 8.78% change. The Chairman of Board of Directors, Amantin and Kasei Community Bank, Dr. John Oduro-Boateng, disclosed this during the 18th annual general meeting of