Accra-Tema Beach Road Expansion Project: Govt pays GH¢3.6m in compensations

 


The government has paid GH¢3.6 million in compensation to persons affected by phase one of the Accra-Tema Beach Road Expansion Project.

The project contractor, China Ganzu International Corporation for Economic and Technical Cooperation (CGICETC), has revealed that the compensation covered buildings and other structures demolished to make way for the project.

The payments were made in two tranches to 36 individuals who received between GH¢4,160 and GH¢429,100 each.

The first tranche of GH¢2.35 million was paid to 16 property owners, while the second tranche which amounted to GH¢1.31 million was paid to 20 property owners.

The completion of the project, originally scheduled for December this year, has been rescheduled to April 2023.

The Administrator of the project contractor, Tracy Tao, indicated that the delay had come about as a result of some difficulties associated with the relocation of utility lines and the demolition of structures on the construction path.

Those, she said, included the relocation of some electricity and water lines, as well as the the removal of some underground tanks of some filling stations along the stretch.

Tao mentioned that there were still some compensations yet to be paid for the removal of two filling stations along the stretch.

She said the construction firm was waiting for the payments to be made and a clearance permit to have the filling stations removed.

Work in progress

Currently, the single carriageway is taking shape as a dual carriageway.

Ongoing works include the construction of a bridge at the A-Life Junction at Teshie and other auxiliary works.

Majority of the works on the stretch from the Nungua Barrier to the railway crossing near the Tema Port had been done.

A three-tier interchange at the Nungua Barrier is also progressing steadily.

Scope of work

Work on the 16-kilometre project, which starts from the Independence Arch of the Black Star Square in Accra through Osu, La and Teshie to Nungua, is being undertaken by CGICETC, while the second phase of 10.6 kilometres — which spans Nungua to Tema Community Three — is being handled by China Railway

Major Bridge Engineering Group Company Limited (CRMBEGCL).

The scope of work includes a two-way, four-lane urban road; a traffic signal system and related auxiliary works.

The 26.6-km project, which is estimated at $100 million, will serve as a major alternative route to the Accra-Tema Motorway.

 

Comments

Popular posts from this blog

Nestlé Ghana Limited Wins Overall Best Industrial Company Of The Year at 13th AGI Industry & Quality Awards

  Nestlé Ghana Limited has been honored with four prestigious awards at the 13th Association of Ghana Industry and Quality Awards ceremony. The event, held in an esteemed setting, gathered prominent figures from Ghana’s industrial sector. Amidst the anticipation, Nestlé Ghana emerged as one of the evening’s notable winners, securing accolades in several key categories. This recognition underscores Nestlé Ghana’s relentless pursuit of excellence and innovation, marking a significant milestone that highlights the company’s substantial contributions to the manufacturing industry in Ghana. Nestlé Ghana's exceptional performance was acknowledged with the following awards: Overall Best National Quality Award, Diamond Category (Food) Overall Best Practices in Sustainable Manufacturing Best Company (Food Sector) Overall Industrial Company of the Year, affirming its status as a leader not only within the food sector but also across Ghana's entire industrial landscape. This success is a ...

Anglogold Ashanti Obuasi Mine tops 2024 Sustainability & Social Investment Awards

 AngloGold Ashanti Obuasi Mine has confirmed its status as sustainability champions by sweeping nine awards, the most won by a company at the 2024 Sustainability & Social Investment Awards (SSI) held at Movenpick Ambassador Hotel in Accra. The feat comes on the heels of a dominant performance in last year's event where AngloGold Ashanti Obuasi Mine swept seven awards. The SSI Awards organised by Ianmatsun Global Services recognizes the most outstanding sustainability, Corporate Social Responsibility (CSR), Environmental, social, and governance (ESG) initiatives in the country and beyond as well as the best teams and individuals who brought them to life. This year's event, which was the 8th edition, was under the theme "Climate Action Now: Accelerating Decarbonization and Building Resilience". The awards won by AngloGold Ashanti on the night include SSI Company of the Year, Best Company in Women Empowerment (project), SSI Company of the Year ( Environment), Best Co...

Zoomlion Advocates Community & Gender inclusive waste management for Climate Action at COP 29

 Africa's waste management giant, Zoomlion Ghana Limited has advocated for an integrated approach to waste management that considers the interest of community members, women and vulnerable groups. James Deku, a Communications Officer of Zoomlion Ghana Limited made this call at the 29th session of the Conference Of Parties (COP 29) of the United Nations Framework Convention for Climate Change (UNFCCC) at Azerbaijan, Baku whiles speaking on the topic "Community-Driven and Gender Inclusive approaches to waste management for Climate Action ". He said the waste sector is a major contributor of methane emissions which is a potent greenhouse gas causing climate change hence the need to manage waste in a manner that considers the interest of all stakeholders. Zoomlion's waste management model is designed and operated in a manner that considers the interest of all stakeholders. Through a Public Private Partnership (PPP) model, local authorities engage community members in clea...