Accra-Tema Beach Road Expansion Project: Govt pays GH¢3.6m in compensations

 


The government has paid GH¢3.6 million in compensation to persons affected by phase one of the Accra-Tema Beach Road Expansion Project.

The project contractor, China Ganzu International Corporation for Economic and Technical Cooperation (CGICETC), has revealed that the compensation covered buildings and other structures demolished to make way for the project.

The payments were made in two tranches to 36 individuals who received between GH¢4,160 and GH¢429,100 each.

The first tranche of GH¢2.35 million was paid to 16 property owners, while the second tranche which amounted to GH¢1.31 million was paid to 20 property owners.

The completion of the project, originally scheduled for December this year, has been rescheduled to April 2023.

The Administrator of the project contractor, Tracy Tao, indicated that the delay had come about as a result of some difficulties associated with the relocation of utility lines and the demolition of structures on the construction path.

Those, she said, included the relocation of some electricity and water lines, as well as the the removal of some underground tanks of some filling stations along the stretch.

Tao mentioned that there were still some compensations yet to be paid for the removal of two filling stations along the stretch.

She said the construction firm was waiting for the payments to be made and a clearance permit to have the filling stations removed.

Work in progress

Currently, the single carriageway is taking shape as a dual carriageway.

Ongoing works include the construction of a bridge at the A-Life Junction at Teshie and other auxiliary works.

Majority of the works on the stretch from the Nungua Barrier to the railway crossing near the Tema Port had been done.

A three-tier interchange at the Nungua Barrier is also progressing steadily.

Scope of work

Work on the 16-kilometre project, which starts from the Independence Arch of the Black Star Square in Accra through Osu, La and Teshie to Nungua, is being undertaken by CGICETC, while the second phase of 10.6 kilometres — which spans Nungua to Tema Community Three — is being handled by China Railway

Major Bridge Engineering Group Company Limited (CRMBEGCL).

The scope of work includes a two-way, four-lane urban road; a traffic signal system and related auxiliary works.

The 26.6-km project, which is estimated at $100 million, will serve as a major alternative route to the Accra-Tema Motorway.

 

Comments

Popular posts from this blog

MTN Ghana & MTN MoMo CEOs win laurels at Ghana CEO Awards

  The Chief Executive Officer of MTN Ghana, Selorm Adadevoh ,   has been adjudged  CEO of the Year  –  Telecom  at the  2 nd  edition of the  Ghana CEO  Vision  and  Awards   held  in Accra. At the same event, the CEO of Mobile Money Limited (MTN MoMo), Shaibu Haruna was also adjudged CEO of the Year – FinTech Service Provider. Selorm  Adadevoh’s award  is in recognition  of  his   achievements   in the areas of   sustainability, leadership excellence, innovation and others  in the telecoms space  which  has contributed to  job creation to support the  growth of Ghana’s economy. Patrick Afari (r), General Manager, Supply Chain Management and General Services receiving CEO of the Year – Telecom Award on behalf of Selorm Adadevoh Receiving the award on behalf of Selorm, Patrick Afari, General Manager, Supply Chain Management and General Services ,  expressed appreciation to the organizers for the award. He  noted that  th e  award will go a long way to inspire MTN to do more for Ghanaian

EB-ACCION DISBURSES US$15 MILLION

By Fred SARPONG Ecobank-Accion (EB-Accion), a partnership between Ecobank Ghana Limited and Accion International has disbursed amount to the tune of $15 million to over 36,000 borrowers in Micro, Small and Medium Enterprises (MSMEs) sector in the country, since the institution was set up barely six months ago. Frances Adu-Mantey, the Managing Director of EB-Accion disclosed this to Business Week in Accra last week during the official opening of Accion Hub headquarters in Africa. The institution’s current portfolio stands at GH¢4 million. She stated that currently, EB-Accion have over 6100 customers who save with them throughout the four branches of the institution. According to her, in order to improve the services of the institution, Ecobank Share Services center will facilitate the technology aspect of the bank by networking all the branches of EB-Accion. Maria Otero, President and Chief Executive Officer of Accion International said that the center’s staff in Accra will provide supp

Amantin & Kasei Community Bank posts impressive growth, with over GH¢1m profit

 Amantin and Kasei Community Bank, at Amantin in the Bono East Region has posted impressive growth in all the performance indicators during 2022 financial year under review. The bank recorded profit after tax of GH¢1,055,662, representing 35.66% more over the 2021 figure of GH¢778.151. This achievement stemmed out of 49.24% gross income growth from GH¢8,143,526 to GH¢12,153,537. Total deposits of the bank went up by 36.20%, changing from GH¢50,959,848 in 2021 to GH¢69,405,591 in 2022. The bank increased loans and advances by 22.15% from GH¢14,128,017 to GH¢17,257,614. Total assets showed an appreciation of 29.32%, amounting to GH¢77,918,288 as against GH¢60,250,693 in the previous year. On the other hand, the bank posted a marginal increase in short term investments portfolio from GH¢24,439,761 to GH¢26,585,698, indicating 8.78% change. The Chairman of Board of Directors, Amantin and Kasei Community Bank, Dr. John Oduro-Boateng, disclosed this during the 18th annual general meeting of