Accra-Kumasi Expressway to be completed December 2028 – Ing. Ahlidza

 Accra-Kumasi ExpresswayThe Managing Director of the Accra-Kumasi Expressway Limited, Engineer Francis Ahlidza, has announced that the 175.6-kilometre Accra-Kumasi Expressway is expected to be completed by December 2028.

Engineer Ahlidza said the  project is being structured around a two-year construction period, with physical works expected to commence in January 2027 following the completion of the procurement and contractor selection processes.

Speaking on the Citi Breakfast Show on Tuesday, September 15, Engineer Ahlidza disclosed that the procurement process for the contractors has already commenced, with firms being invited to express their interest in undertaking the major road project.

He explained that the selection process will be conducted in two stages and will involve international competitive procurement to ensure that qualified firms are selected for the project.

We are working with a two-year construction period starting at the end of this year. We have started the procurement process by requesting for firms to express interest which is an international competitive process but we will do that in two stages.

“We expect to close this at the end of the year so that the contractors can start working in January 2027 and complete by December 2028.”

Engineer Ahlidza’s timeline means that, barring significant delays in the procurement and construction processes, motorists could begin using the completed expressway by the end of 2028.

Project Management Software

The announcement comes a day after the official right-of-way handing-over ceremony for the project was held on Monday, September 14.

The Accra-Kumasi Expressway is expected to significantly transform road transportation between the two major cities and improve connectivity along one of Ghana’s busiest economic corridors.

The 175.6-kilometre road project is also expected to improve the movement of people and goods, reduce travel times and enhance road safety for motorists who regularly use the Accra-Kumasi route.

According to details provided on the project, the expressway will feature eight grade-separated interchanges, 11 vehicle overpasses and 55 mainline bridges.

Comments

Popular posts from this blog

NESCAFÉ Launches Real Vibes Text & Win Promo to Reward Coffee Consumers Across Ghana

 NESCAFÉ has launched the Real Vibes Text & Win Promo, an exciting consumer promotion designed to reward loyal coffee lovers and bring the brand’s My Coffee, My Vibe experience even closer to consumers across the country. Running from September to December, the promotion gives consumers the opportunity to enjoy their favourite NESCAFÉ coffee while standing a chance to win exciting prizes, including phones, motorcycles, airtime and the ultimate grand prize—an electric SUV. Speaking at the launch, Lily Ntim, Category Development Manager for NESCAFÉ, said the promotion reflects NESCAFÉ’s commitment to creating, rewarding and memorable experiences for consumers. “Today, we are excited to introduce the NESCAFÉ Real Vibes Text & Win Promo, a campaign designed to bring the My Coffee, My Vibe experience even closer to our consumers,” she said. She added that the campaign is not only about prizes, but also about celebrating the everyday moments consumers enjoy with their coffee. “T...

Ghana Home Loans

With interest rates declining, a more liquid environment and a macroeconomic stability, mortgage financing is expected to see an ease of credit. And Ghana Home Loans being a leader in this industry is expected to lead the way. Ghana Home Loans (GHL), a leader in home mortgage, continues to be the frontier in fulfilling dreams of many Ghanaians in homeownership. Since starting business in 2006, it has also provided many existing homeowners with Equity Release mortgages to support their businesses, pay educational fees, improve their properties, or simply pursue other personal hobbies and interests. Ghana Home Loans is a mortgage finance institution which operates under Bank of Ghana’s supervision as a non-bank financial institution. At present, the Company remains the only such institution that focuses exclusively on the provision of mortgage product. Through the Home Completion mortgage and Home Construction mortgage products, Ghana Home Loans has enabled many qualified applican...

Tender Committee recommends E&P for Damang Mine lease transfer

  A Tender Committee has recommended the grant of the mining lease for the Damang Gold Mine to Engineers and Planners Limited, following a competitive evaluation process conducted by the Minerals Commission. The recommendation comes after a tender process initiated under Regulation 258 of the Minerals and Mining (Licensing Regulations), 2012 (LI 2176), aimed at selecting a strategic investor to take over the mining lease and operations of the Damang mine. According to the report, four companies responded to the public tender announced in the media. Out of these, two firms were shortlisted by the Mineral Titles Department of the Minerals Commission and subsequently submitted to the Tender Committee for detailed assessment. After what was described as a comprehensive evaluation, Engineers and Planners Limited emerged as the highest evaluated bidder, leading to the Committee’s recommendation for the award of the lease. Gold Fields Ghana Limited, which has operated in the country since...